Paper Mill Avoids Increasing Electrical Infrastructure

A paper mill customer wanted to buy a new 250KVA winder but found out that there was not enough current capacity available in their switchboards to support the new winder. A power system study reveled that power factor correction would reduce the current through his switchboards giving the capacity needed for the new winder.

Download this case study >>